Pembuatan Saluran Air di Jl Rorotan V Capai 50 Persen

Channel Project at Jalan Rorotan V Still Reaches 50 Percent

North Jakarta Sub-dept. of Water Management provides water channel at Jalan Rorotan V RW 05, Rorotan Urban Village, Cilincing. The channel length is 323 meters.

The water can not flow due to no water channel

Since the early construction in July, now the process has reached 50 percent or 135 meters.

North Jakarta Head Sub-dept. of Water Management, Herning Wahyuningsih, said the channel project is based on local citizens request. The area is always flooded by 30 cm during rainy season.

Channel & Conduit Around Presidential Palace Cleaned

“The water can not flow due to no water channel,” she said, Wednesday (8/10).

According to her, the project is targeted to complete in September

Linked News
Popular News indeks
  1. Jakarta Taps MSMEs and Creative Economy to Secure Global Top 50 Spot

    access_time11-07-2026 remove_red_eye1713 personAldi Geri Lumban Tobing
  2. Ciliwung River Normalization Accelerated, Pramono Ensures Land Acquisition Without Intermediaries

    access_time10-07-2026 remove_red_eye1483 personDessy Suciati
  3. Blocked Drain on Jalan Palmerah Utara is Being Repaired

    access_time10-07-2026 remove_red_eye1336 personFolmer
  4. Pramono will Take Firm Action Against Individuals Involved in Extortion

    access_time13-07-2026 remove_red_eye1121 personDessy Suciati
  5. The Pegangsaan Dua-Manggarai LRT Project Reaches 95 Percent Completion

    access_time14-07-2026 remove_red_eye816 personDessy Suciati